Project Status
UPDATE: The 2019 Bond project at Bailey Junior High is in construction. The new parking lot off of Bowen Road is now complete and construction on the two additions, along with renovations in the existing building, is ongoing.
The bricking for the additions is 90% complete. The kitchen expansion is dried in and the drywall is in process. The classroom and new entrance addition should be dried in soon.Â
The east parking lot is also currently being redone and many of the interior renovations will be done over the summer.
Read more about Bailey's construction.
Project Scope
- Heating & A/C, electrical, plumbing improvements
- Interior renovations (Flooring, ceilings, lighting, windows, etc.)
- ADA accessibility improvements (Door hardware, elevators, ramps, restrooms, etc.)
- Restroom renovations
- Site improvements (Lighting, landscaping, drainage, irrigation, signage, etc.)
- Paving improvements
This list is not comprehensive and is subject to change.
- Classroom addition
- Kitchen and cafeteria addition
- Instruments & Uniforms
- Visual Arts Upgrades
- Athletic Facility Improvements (Gymnasium, lockers, field concessions/restrooms/storage, etc.)
This list is not comprehensive and is subject to change.
- Expanded Security Camera Coverage and Upgraded Camera Software
- Safety & Security Enhancements (Exterior and interior key system upgrades, district communication system upgrades, lighting, fencing, etc.)
- Device Upgrades, Student Calculators, Expanded Access
This list is not comprehensive and is subject to change.
PHASE
Phase 2
CONSTRUCTION
Start: Spring 2023Â Â Â Finish: Fall 2024
ARCHITECT
LBL Architects
CONSTRUCTION MANAGER
RJM General Contractors